BRT Abdul Sattar Edhi Line (Orange Line)
From Town Municipality Administration (TMA), Orangi to KDA Roundabout North Nazimabad, Karachi.
Project Background
- Orange BRT starts from Town Municipal Administration Office (Orangi Town) to Jinnah University for Women, Karachi (near Matriculation Board Office)
- M/s NESPAK is the Detailed Design and Construction Supervision consultant of SMTA
- The project alignment is of88 Kilometers including four (04) BRT Stations and one (01) Bus Depot (adjacent to Paposh Graveyard).
- The procurement of Intelligent Transport System (ITS) and 20 BRT Buses as well as BRT Operations for three (3) years have been mandated to the SIDCL (through Facilitation & Implementation Agreement between SIDCL and GoS) and the provision of funds has been included in Revised PC-1 of the project, approved in 2021.
The Project is contractually divided in following packages :-
|
Contractor |
M/s MS Engineering Services Pvt. Ltd (Package-1) |
M/s KNK Pvt. Ltd. (Package-2) |
|
Tender Invited |
May 2016 |
May 2016 |
|
Award of Work |
June 2016 |
October 2016 |
|
Awarded Bid Cost |
PKR 643.35 million |
PKR 496.76 million |
|
BRT Corridor |
Total 3.88 KMs including 1.5KM of Bacha Khan bridge |
|
|
Number of Bus Stations (04 Nos) |
Total 4 stations. 2 in Package 1 and 2 in Package 2. Only 1 station is elevated adjacent to TMA office. |
|
Bus Depot |
3 acres next to Paposh Graveyard |
|
Package # 3 (contract awarded to M/s Muhammad Ramzan & CO)
- Package-3 work scope comprises on the procurement of 350 KVA Generator and Platform Screen Doors (for operational integration with the Green BRT project as communicated by the SIDCL).
- The Bid Cost is PKR 165.87 million.
Status of Package # 4 (contract awarded to M/s Taj Construction)
- Package-4 work scope comprises on Construction of Underground Fuel Tank, Steel Shed, IITS Conduits (for operational integration with Green BRT), Waste Water Treatment Plant (compliance with the SEPA requirement) in Bus Depot.
- The Bid Cost is PKR 63.26 million.
PC-1 Status
Original PC-1 Cost (January 2015): PKR 2.364 billion (including Infrastructure, Procurement of Buses and ITS – note that bus operations were not included)
Revised PC-1 Cost (April 2021): PKR 4.290 billion (including Infrastructure, Procurement of Buses and ITS and Bus Operations for 3 years)
Revised PC-1 includes: PKR 2.120 billion to be given to the SIDCL for procurement of 20 buses and ITS equipment as well as Bus Operations of Orange Line for 3 years.
|
Infrastructure Component |
2,170,336,293/= |
Includes cost of complete civil works. |
|
Buses |
737,266,560/= |
For 20 buses including 36% taxes and at 1 USD = Rs 160 |
|
ITS |
441,112,626/= |
Procurement of ITS including 30% taxes |
|
Opex |
368,321,336/= |
|
|
Others |
573,736,042/= |
Includes Consultancies, Administrative charges, Insurance, Contingency |
|
TOTAL |
PKR 4.290 billion |
Cost of Revised PC-1 approved in April 2021 |
Current Status
The Project was inaugurated by Honorable Minister Transport & Mass Transit Department, Government of Sindh on 10th September 2022. Formal Bus Operations were commenced on the same day by the SIDCL.
Bus Operator = M/s Daewoo Pakistan Express Bus Service Ltd.
Bus Manufacturers = M/s Zhong Tong Bus Holding Co. Ltd
Intelligent Transport System = M/s NRTC JV M/s KENTKART (Package A) and Consortium of M/s NLC and M/s MGH Engineering Pvt Ltd. And M/s Wavetec Pvt. Ltd (Package B)
Consultants:
- M/s Exponent Engineers Pvt. Ltd JV M/s EY JV M/s HaiderMota
- M/s BLIC JV M/s EA Consulting Pvt Ltd. JV M/s DCC Pvt. Ltd Karachi
- M/s EA Consulting (the Engineer) on behalf of the SIDCL
- M/s NESPAK (the Engineer) on behalf of the SMTA